Is the SkyTrain really coming to Langley? This is a question that I get asked from time to time, and the answer is yes. While funding is currently only available to build the extension of SkyTrain to Fleetwood today, work is actively underway to secure the funding required to get the line built to Langley.
Map of proposed SkyTrain extension to Langley. In two stages. Select map to view. |
One of the first steps to securing funding is to complete the business case to build SkyTrain to Langley. TransLink management is providing an update to the TransLink board later this week, including the latest updates on expending SkyTrain along Fraser Highway.
Full Scenario: King George to Langley City Centre | Fleetwood Scenario: King George to 166 St | |
---|---|---|
Scope | 16 km 8 stations 55 vehicles |
7 km 4 stations 25 vehicles |
Ridership | 62,000 in 2035 71,200 in 2050 |
39,900 in 2035 44,200 in 2050 |
New transit trips | 24,000 in 2035 30,000 in 2050 |
12,000 in 2035 14,000 in 2050 |
Benefit cost ratio | 1.24 | 1.12 |
Capital cost* | $3.12 billion | $1.63 billion |
Annual operating cost† | $32.4 million | $17.0 million |
Annual fare revenue† | $21.3 million | $10.2 million |
In-service date | 5.5 years fromproject approval | 5.5 years fromproject approval |
Work done since earlier this fall includes:
- Completing a corridor geotechnical investigation program
- Completing a reference case design
- Completing studies to support the project environmental screening review
- Completing risk workshops, risk analysis and industry market sounding to support assessment of procurement options
- Initiated briefings with senior government on elements of the draft business case
- Advanced negotiation of agreements with Surrey, Langley City, and Township of Langley
- Advanced Operations and Maintenance Centre (OMC) programming and site assessment analysis
- A second round of public engagement
The business case for this SkyTrain extension will be completed early next year. Once the business case is signed-off, formal funding agreements will be drafted with the federal and provincial governments. Once complete, an 18-month procurement process will start for building SkyTrain to Fleetwood, followed by a 4-year construction, testing, and commissioning period.
The federal and provincial governments have pledged their support for the Mayors’ Council transit vision which includes building SkyTrain to Langley. The missing funding to build to Langley is the regional portion. The Mayors’ Council will need to figure out the right combination of property tax, gas tax, and/or development charges to complete their full transit vision which includes SkyTrain to Langley. I’m optimistic that they will be able to sort this out next year.
* Year of expenditure, costs for project completion to Langley will increase the longer construction is delayed
† 2019 dollars